
Environmental Sludge Sampling, South London
Appointed as Principal Contractor to
investigate and establish the depth profile and characteristics of three
sludge lagoons, adjoining a waste water treatment and sewage works, with
sampling of potentially hazardous surface liquor, sludge, and the underlying
(clay) base. All works carried out from floating platforms and successfully
completed within 4 weeks.
read
more
Tunbridge Wells Gasworks, Kent
Ground conditions on this 3Ha site comprised Made Ground over Wadhurst Clay with several former gas works structures intact below ground level. The soils, and locally groundwater, were found to be contaminated with arsenic and PAH's, TPH, BTEX compounds, phenols, cyanide and ammonia and certain solvents. The remedial design included bioremediation of 30,000 m3 of contaminated soils, construction of ingound barriers (impermeable and semi-permeable) and re-engineering of an existing culvert stream as an open channel feature across the site. Southern Testing managed the project and undertook all verification works.
Brownfield Briefing
Remediation Innovation Award 2006 - In 2006, the project won a
Brownfield Briefing Remediation Innovation Award for "Best Use of Combined
Systems". Judges
Comments: " This
project demonstrates tremendous collaboration. It was homogeneous and well
managed bringing benifits off site as well as onsite " John Cambell " Two
tried and tested technologies brought together in a best practice manner..a
well presented submission which gives due credit to those who actually
carried out the remediation " Clive Boyle.
read
more
Hampton Court Gasworks, Middlesex
This 2Ha site was to be redeveloped with 198 residential apartments, a 72 bed nursing home, and around 800sqm of mixed-use offices and commercial developments. The underlying geology consisted of Terrace Gravels over London Clay and the site investigation indicated the site was heavily contaminated. Southern Testing were appointed to manage, co-ordinate and validate all remediation works.
Brownfield Briefing
Remediation Innovation Awards 2008 - Southern Testing were Runners Up
in the Category ' Best use of a Combination of Remediation Techniques'
at the 2008 Brownfield Briefing Remediation Innovation Awards for their
work at the Former Hampton Court Gas Works Site. The Judges noted that
: "the
project demonstrated strong application of cutting edge techniques to
a very traditional site problem and praised its design and management".
The category winners were Olympic Park Authority for the Olympic Park
Project.
read
more
Site Appraisal of Former Quarry, Kent
Pre-planning investigation assessment
of a 4ha site, that adjoined a landfill and had historically been backfilled
with a variety of waste materials.
read
more
Brownfield Development & Asbestos Remediation, Kent
The initial walk over survey of this
former hospital site identified Asbestos Containing Materials within the
fabric of remaining buildings, in collapsed below ground duct runs and
in demolition rubble across the site. The strategy proposed a systematic
and careful removal of “point
sources” or “hot
spots” together with other remedial measures to safe guard site end
users. Southern Testing
managed the project and undertook all validation works to obtain regulatory
signoff.
read
more
Rubber Works, Surrey
This 2.9Ha site was to be redeveloped
for housing with private gardens. Following an investigation, groundwater
monitoring identified toluene contamination in the shallow
fluvial aquifer beneath the site, along with trichloroethylene contamination
in an underlying Tertiary sand aquifer. Southern Testing were able to recommend
a programme of in-situ treatment of the groundwater and supervised and
validated the remediation works to obtain regulatory approval.
read
more
Petrol Station, South London
Boreholes and test pits indicated soils and groundwater were contaminated with heavy metals, poly aromatic hydrocarbons (PAHs), and petroleum hydrocarbons. Insitu remediation was carried out in-situ during the re-development phase using a combination of air sparging and soil vapour extraction. The programme was monitored for nine months and was successfully ‘signed off’ by the regulators in advance of property completions.
Local Authority Part IIA Land Fill Investigation
The Local Authority proposed to upgrade the existing facilities at the recreation ground site. Preliminary intrusive investigation had identified potentially contaminated land resulting from the sites former use as a Chalk Pit, which was later infilled with incinerated domestic wastes. A scope of works was designed in conjunction with the Local Authority with the object being to provide cost effective inspection of the site to assess the likely nature and extent of contamination, taking into account the current identified risks and the costs of site mobilisation, chemical analysis and reporting.
A flexible approach was adopted that allowed the inspection strategy to be reviewed and refined as necessary based on the findings of the Phase 1 Desk Study and as site works progressed. These comprised the assessment of the effectiveness and chemistry of the existing site capping layers given the current and proposed site use. Preliminary investigation to profile the depth of waste (made ground) across the site and preliminary land gas and leachate monitoring.
Local Authority Part IIA Preliminary Site Inspection and Reporting
Part IIA Preliminary Site Inspection and Reporting across various sites. Desk study and preliminary ground investigation to establish potential risk from historically backfilled ponds / earthworks features. Installation of monitoring wells, gas monitoring, chemical analysis, risk assessment and interpretive reporting.
Local Authority Part IIA Data Analysis
Part IIA investigation of a former Engineering Works that was redeveloped in the 1980s with residential properties. The scope of works comprised an enhanced desk study using data provided by the Local Authority and estimating / scoring the likelihood of a pollutant linkage. A statistically robust sampling plan was then produced allowing a preliminary site investigation comprising trial holes excavated on site using hand auger and windowless sampler equipment. Limited chemical laboratory testing was undertaken. Following successful application for DEFRA funding, additional investigation was undertaken by others, and we undertook analysis of the combined chemical data sets.
Local Authority Part IIA Site Prioritisation
Prioritisation of previously identified
land that might be contaminated, in line with the Councils legal duty under
Part IIA. Our strategy was to use standard GIS systems to capture relevant
source data. We then produced enhanced desk studies for key sites incorporating
a full risk-scoring conceptual model with all significant pollutant linkages
scored and ranked. Additionally, data collected within the GIS was used
to allow zoning of the sites for physical inspection, and to produce statistically
robust inspection options. Based on this information, we were then able
to produce an overall budget for the most cost effective inspection of each
of the key sites, taking into account the identified risks and the costs of
mobilisation. We completed the task for over 1600 sites, which included over
64 landfill sites in less than 4 months.
read
more